Here’s a general breakdown, courtesy of University Media Relations, of where the $2.9 million Uncle Barry’s giving to the University is going.
Mechanical Upgrades and Replacement Projects
1. Pacific Hall Sprinkler – 1st and 2nd Floor (new fire sprinkler system to the building)
2. Steam and Chilled Water Control Valves (various locations) – (valves required to further regulate our heating and cooling systems campus wide)
Electrical Upgrades and Replacements
1. Central Electrical System Transformer Replacements (7 locations campus-wide)
2. Romania-ODOT/DPS Network infrastructure (Telecommunications upgrades)
Exterior Building Repairs
1. Friendly Hall Exterior Renovation
Programmatic Modifications
1. Building 130 Interior Reconfiguration (office space expansion and reconfiguration)
Deferred Interior Finish Replacements – (Campus-wide finish upgrades of common-use spaces)
1. Zone A Carpet and Paint Replacements
2. Zone B Carpet and Paint Replacements
3. Faculty Office Renovations
Code and Safety Upgrades
1. Sidewalk Replacements (various campus-wide locations to reduce trip hazards)
Some stories not covered; The future move of DPS to a area far South of campus(ODOT property-almost to Glenwood), the work now taking place on the campus power plant, the opening date for the segregated athlete learning center, the 16th and Moss dorm, the Walnut Station mixed-use development area, the indoor track proposal(site and funding source), the UO Duck shop land swap with the UO Foundation affiliated Guistina family.